Project Description
Apartment Renovation in Ampelokipoi
After architectural and decorative design and with the prospect of renting the apartment through the AIRBNB platform for its best use, and for maximum return on investment and functionality, concealed lighting in the living room, a concealed-roof construction was constructed. as well as a suspended ceiling on the ceiling of the kitchen. There was also a hidden ceiling lighting in the master bedroom. In our constructions we used LED tapes as well as spotlights. Let’s mention how using new technologies such as card locking, thus minimizing property costs, since it allows us to ‘close’ the general home when tenants leave, and there is no unnecessary power consumption when the apartment no occupants (eg open and forgotten air conditions, water heater, kitchen, stereo, TV etc)
The house has been renovated and completely renovated in all areas, with the result that it justifies the options, since we are now talking about a new modern and modern apartment.
The renovation begins with the demolition of the walls in the hall near the entrance and we continue with the living room wall to unify the space.
We continue with the demolition of the old bathroom wall
where new partitioning took place, and a cloakroom was built, as well as a new bathroom for the master bedroom.
The new kitchen was installed in a new space, after the complete dismantling of the old plumbing and electrical installation.
We made the new kitchen from hpl high gloss acrylic door. A new wardrobe in the bedroom with a door and a dressing room made of baklite lpl was also built.
The entire old electrical installation was completely dismantled and a new home electrical network was built from scratch. New electrical pipes, new patient and high current, bi-zonal alarms, new HAGER board with HAGER fuses, also HAGER digital voltage monitor, new grounding and a complete new electrical installation.
Following the dismantling of the old flooring throughout the house, new gress porcelanato tiles were installed throughout the house, as well as in the bedrooms, after all the wooden floors had dried up and a self-leveling wrap was applied to the filling and leveling. floor of the house.
The old bathroom, all the old plumbing and electrical installations, pipes and drains were completely dismantled and refurbished, and two new modern bathrooms with new hydraulic-drainage and electrical installation and a separate water table were built from scratch.
New sanitary ware, batteries and a cabin with a safety glass were installed
All interior doors were replaced with new type laminate hpl doors with door frames and sill windows, as well as the loft door and the front door of the house with a new 16-point double shield door and dual catapult lock and card lock.
All the old exterior wooden frames of the apartment were replaced and new europa-brand energy-efficient recessed aluminum windows with electric shutters and screens were installed.
Before installing the new floors, we had a completely new underfloor single-tube heating system and the bodies were now placed in the new correct loss points. New panel bodies of the delonghi panel were also installed
We trimmed, weeded and plastered all the walls of the house, primed at least two hands with a special primer to avoid any future shading and then painted all areas with ecological and washable colors. The exterior walls of the house were all painted in acrylic paint.
Completing, after wishing our customers and friends first, ‘summer’ with a new modern apartment and a thorough and complete home renovation by G + G GROUP.
I would like to personally thank them for our excellent cooperation throughout the renovation, from start to finish.
Completion time 70 days.
SINCERELY
G + G GROUP
THEODOROS GOUCHETIS
Below you can see some photos showing the project in its early stages and the final result